Pre-Thanksgiving opening in sight for Loblaws store under construction inside Maple Leaf Gardens

Facebooktwitterredditpinterestlinkedinmail

Maple Leaf Gardens

June 14 2011: Carlton Street view of Maple Leaf Gardens, looking northwest

 

Talking turkey: If all goes according to plan for the Maple Leaf Gardens revitalization project, downtown residents will flock to the historic hockey shrine to shop for Thanksgiving turkeys this fall. Construction of a 70,000 square foot Loblaws grocery store inside the Gardens fell behind schedule this year (it was supposed to be open by now), but I’ve been told that Loblaws anticipates work will finish within the next three months. The goal is to open the store by summer’s end so Loblaws can cash in as shoppers rush to fill their kitchen cupboards for the Thanksgiving holiday weekend. On the other hand, a completion date remains far from certain for the Ryerson University Sports and Recreation Centre, which is being built on two levels directly above the Loblaws store, since substantial construction work remains to be done there. When I got a peek inside the ground level of the Gardens a few days ago, I didn’t think the Thanksgiving target would be achievable.  When I asked one of the site supervisors if work would be finished by October, he chuckled and said: “As we say in construction,  ‘it will be finished when it’s finished.'” But another man in a white hard hat told me that once the “shell” of the grocery store is finished, which he said should happen soon, the grocery store interior will take shape rapidly.

Meanwhile, there’s a lot happening outside the Gardens, too. Scaffolding that has shrouded much of the building’s south wall along Carlton Street is gradually being dismantled as crews complete window installation and work on the brick facade. From street level, the most noticeable change has been the removal of the long blue and silver Maple Leaf Gardens marquee above the main entrance; it will be replaced. Just around the corner, southbound traffic on Church Street is disrupted frequently when portable cranes pull up to hoist steel bars and other building materials for the Ryerson sports complex onto the Gardens roof (a supervisor said that’s how most construction supplies must be loaded into the Ryerson section of the Gardens now that the grocery store has filled out most of the ground level).  The dome atop the Gardens roof is being refurbished, too, and once that is done, a new maple leaf logo will be painted on the broad white surface and Canadian flags will be raised to flutter from the empty rooftop flagpoles. Below are photos I have shot since late April of construction activity outside and on top of Maple Leaf Gardens. To view photos of earlier stages of construction, check out my posts from April 14 2011, March 29 2011, and February 2 2011.

 

Maple Leaf Gardens

April 29 2011: Roof work underway on the north side of the Gardens’ dome

 

Maple Leaf Gardens

April 29 2011: Another view of revitalization work on the roof of the Gardens

 

Maple Leaf Gardens

April 30 2011: Scaffolding covers the middle third of the Maple Leaf Gardens south wall along Carlton Street. The Canadian flags and the blue and silver marquee above the main entrance will be removed as work proceeds on the building.

 

Maple Leaf Gardens

April 30 2011: Scaffolding rises from the marquee above the main entrance all the way to the top of the building’s south wall.

 

Maple Leaf Gardens

April 30 2011: A view of the main entrance before the marquee is removed

 

Maple Leaf Gardens

April 30 2011: Window replacement and brickwork is underway behind the shrouds

 

Maple Leaf Gardens

April 30 2011: The sidewalk and one westbound lane on Carlton Street have been closed so crews can finish exterior work on the Gardens

 

Maple Leaf Gardens

May 13 2011: Construction workers on the roof of Maple Leaf Gardens

 

Maple Leaf Gardens

May 13 2011: Workers atop the dome’s northeast corner above Church Street

 

Maple Leaf Gardens

May 13 2011: A truck pumps concrete through the Maple Leaf Gardens roof and into the Ryerson University sports complex being built on the upper two levels

 

Maple Leaf Gardens

May 13 2011: Concrete pumper above the southeast corner of Maple Leaf Gardens

 

Maple Leaf Gardens

May 13 2011: Pumpcrete vehicle delivering concrete for the sports complex

 

Maple Leaf Gardens

May 13 2011: The long boom of the Pumpcrete truck rises to the roof

 

Maple Leaf Gardens

May 13 2011: A closer view of the Pumpcrete machine

 

Maple Leaf Gardens

May 13 2011: A concrete truck outside the Gardens’ Carlton Street main entrance

 

Maple Leaf Gardens

June 1 2011: A crane hoists a load of steel bars to the roof of the Gardens

 

Maple Leaf Gardens

June 1 2011: A worker guides the load to the rooftop

 

Maple Leaf Gardens

June 3 2011: With the roof recovered, brickwork proceeds on the north wall

 

Maple Leaf Gardens

June 3 2011: Workers replace a window on the Wood Street wall of the Gardens

 

Maple Leaf Gardens

June 14 2011: A crane hoists building materials to the roof of Maple Leaf Gardens

 

Maple Leaf Gardens

June 14 2011: Another load of construction material rises to the rooftop

 

Maple Leaf Gardens

June 14 2011: Two construction workers watch as the crane hoists its load

 

Maple Leaf Gardens

June 14 2011: Workers watch and wait while the crane hoists supplies to the roof

 

Maple Leaf Gardens

June 14 2011: Scaffolding rises up the south side of Maple Leaf Gardens

 

Maple Leaf Gardens

June 14 2011: The scaffolding is gradually being removed as brickwork is finished

 

Maple Leaf Gardens

June 14 2011: A metal frame (bottom) is all that remains of the long blue and silver marquee that used to hang above the Gardens’ Carlton Street entrance

 

Maple Leaf Gardens

June 14 2011: Another view of scaffolding above the Carlton Street entrance

 

 

 

 

7 thoughts on “Pre-Thanksgiving opening in sight for Loblaws store under construction inside Maple Leaf Gardens

  1. cara

    i’m glad you’re keeping tabs on this project – doesn’t seem like too many people are. i personally can’t WAIT for this loblaws to open, as i live right across the street in one of the condos, and grocery stores in this area are extremely limited. currently there is only the metro underneath at college park, and its selection is pretty horrible.

    Reply
    1. TOblogeditor Post author

      The College Park Metro store is awful — the aisles are far too narrow and the shelves stacked far too high. The store is always congested and feels like being inside a TTC subway train during rush hour. That entire level of College Park is far too busy almost any time of day — I’ve nearly been trampled just trying to get into and out of the store. I really dread the thought of walking through College Park once the Aura condo tower is occupied, and thousands more people start using the mall. I avoid it as much as possible and go to the Metro on Gould Street instead — better selection and easier to move around. I’ll be interested in seeing the Loblaws layout, and hope it’s an open, airy store like the Longos in Maple Leaf Square.

      Reply
  2. CarltonGirl

    I’ll be pleasantly surprised if this thing is actually finished in the fall. I have to walk by like every day and granted I don’t know much about construction but it still looks like a long way from being done to me. Still, if you say it will be done by the fall, I’ll stay hopeful. I’m SO looking forward to this. Like someone else mentioned the Metro is handy for being 24h but damn it’s expensive and seriously lacks selection. I’m so looking forward to this Loblaws!

    Reply
  3. Jeff

    A friend of mine who works for Loblaws told me that they are now planning on an early November opening. He hadn’t heard for sure…but they are aiming for the week of Nov 7. I walk by the store 4 or 5 times a week and the LCBO has a big sign up that reads “Opening Fall 2011”. When I walked by today, I could see inside that they had some of the refridgeration cabinets in place…And probably some of the freezers for the frozen food section. My guess on what I saw today…is mid to late November..but I’m only guessing.

    Reply
  4. M. Holek

    A new Medical & Walk-In Clinic also to open on the main level of the new Loblaws store located at Maple Leaf Gardens.
    It will be open 7 days a week – No appointment necessary!
    Services to include:
    Travel Medicine, Sports Medicine, Allergy & Flu Shots, etc. Rehab Services to start in January 2012

    Reply
  5. Pingback: November opening uncertain for Gardens grocery store | www.TheTorontoBlog.com

  6. Pingback: Maple Leaf Gardens Loblaws store to open on November 30 | www.TheTorontoBlog.com

Leave a Reply to Jeff Cancel reply

Your email address will not be published. Required fields are marked *