September 7 2012: A view of the Motion on Bay Street rental apartment highrise from atop the podium green roof at Toronto City Hall to the south

 

Motion on Bay apartment highrise

September 7 2012: A look  up the tower’s east side, from Bay Street…

 

Motion on Bay apartment highrise

… and a view of Motion from the northwest, along Dundas Street

 

Photo update: Construction of the Motion on Bay Street rental apartment highrise has passed 20 storeys, on its way to a final floor count of 29.

A project of Concert Properties, the 463-unit building is scheduled for completion next spring.

 

CONTINUED ON PAGE 2

Construction of 29-storey Motion on Bay rental apartment highrise passes the halfway point

Motion on Bay Toronto

August 11 2012: Construction of the 29-storey Motion on Bay rental apartment building at Bay & Dundas Streets has reached 17 floors, with 12 more to go

 

Halfway there: If some of the emails I receive are a reliable indication, there’s a lot of people in Toronto who think that the Motion on Bay Street building currently under construction at Bay & Dundas Streets is going to be “yet another condo,” to borrow the words of one correspondent.  After I published some construction photos on May 5, I received several private messages from people requesting information about availability and purchase prices for 1- and 2-bedroom “condos” in the building. (For some reason, a lot of people also assume I’m a condo sales rep.) With this update post, I’m already bracing for another series of similar inquiries.

 

CONTINUED ON PAGE 2

Work reaches 6th floor at Motion on Bay Street

Motion on Bay Toronto

May 5 2012: Construction workers were busy moving building forms today to prepare to build the 6th level of the Motion rental highrise

 

Motion on Bay Toronto

May 4 2012: The building will rise 29 storeys at the SW corner of Bay and Dundas Streets, and contain 463 units plus street-level retail shops

 

Form fitting: The Motion rental highrise at Bay & Dundas Streets reached a new level today, as crews repositioned building forms to prepare for construction of the 6th floor of what will ultimately be a 29-storey tower.

Toronto Police closed Bay Street to traffic for the length of the building site this afternoon while the construction crane hoisted forms from the building’s fifth level, and repositioned them directly above.

 

CONTINUED ON PAGE 2

Pit stops: Checking out excavation activity at Fashion House, Motion Apartments and U Condos

Fashion House condos on King Street West

March 29 2011: Excavation at the NE corner of the Fashion House site

 

Motion on Bay apartment tower

March 22 2011: Motion on Bay apartment tower excavation at Bay & Dundas Streets

 

U Condos condo tower excavation

April 1 2011: U Condos condo tower excavation at Bay and St Mary Streets

 

Digging deeper: Excavations for three new highrise residential buildings are moving steadily along in three different downtown areas.

The digs at Fashion House Condos on King Street West, Motion Apartments on Bay at Dundas, and U Condos on Bay near Yorkville, all are more than one underground level deep at parts of their respective construction sites. But while excavation activity is underway on almost the entire Motion on Bay site, digging is limited to certain perimeter points at Fashion House and U Condos. Pile driving and shoring activity continues at both of those sites, where roughly three-quarters of the ground on each property has yet to be broken.

Below is a series of recent photos showing excavation progress at each building site. To view building renderings and pictures I’ve published previously, see my January 24 post on Fashion House, my January 29 post for Motion on Bay, and my February 4 and March 18 posts on U Condos.

 

Fashion House condos on King Street West

March 29 2011: View from King Street of the Fashion House site

 

Fashion House condos on King Street West

March 29 2011: Activity at the northwest corner of the Fashion House site

 

Fashion House condos on King Street West

March 29 2011: Activity at the northwest corner of the Fashion House site

 

Fashion House condos on King Street West

March 29 2011: Excavation at the north side of the Fashion House site

 

Fashion House condos on King Street West

March 29 2011: Activity at the NE corner of the Fashion House site

 

Motion on Bay Apartments

February 15 2011: Northwest view of Motion on Bay excavation

 

Motion on Bay Apartments excavation progress

February 15 2011: The north half of the Motion on Bay construction site

 

Motion on Bay Apartments excavation progress

March 22 2011: Excavation activity at the SW corner of the Motion site

 

Motion on Bay Apartments excavation progress

March 22 2011: Shoring and excavation equipment at the Motion site

 

U Condos on Bay Street below Yorkville

April 1 2011: Digging away at the southwest corner of the U Condos site

 

U Condos on Bay Street below Yorkville

April 1 2011: Excavator digging at the NW corner of the U Condos site

 

U Condos on Bay Street below Yorkville

April 1 2011: The dig is more than one level deep at U Condos’ western perimeter

 

U Condos on Bay Street below Yorkville

April 1 2011: A closer view of the depth of the excavation at the northwest corner

 

U Condos on Bay Street below Yorkville

April 1 2011: Excavation depth along the property’s western perimeter

 

U Condos on Bay Street below Yorkville

April 1 2011: St Mary Street view of activity at the east end of the site

 

U Condos on Bay Street below Yorkville

April 1 2011: Preparing the Bay Street side of the site for excavation


Excavation work gets in full Motion for 29-storey apartment highrise being built at Bay & Dundas

Motion on Bay

Architectural rendering of Motion in Bay apartment highrise


Now digging: The parking lot is long gone and the earth is starting to move at the southwest corner of Bay and Dundas, where Concert Properties Ltd. has begun building its latest rental apartment building, Motion on Bay Street. 

The 29-storey tower will house 463 rental apartments (mainly studios and 1-bedrooms units) along with ground-level retail shops. The project’s website claims occupancy is anticipated for winter 2012, but that move-in date seems overly optimistic since site excavation is still just in the early stages.

I had been wondering how long it was going to take before a developer began building here, since Motion’s 570 Bay Street address is such a prime downtown location (the Eaton Centre and Ryerson University’s business school are right across the street; City Hall and the Financial District are a short walk to the south, and the hospital district is only two blocks north). It just didn’t make sense to maintain a parking lot on a piece of land worth millions of dollars.

A 50-storey condo tower originally had been proposed for this location as a sister to One City Hall, a 16-storey condo building at 111 Elizabeth Street that will be Motion’s next-door neighbour. However, the city would not approve the project since it would ruins views of Toronto’s beloved City Hall towers immediately to the south. The land was sold (at a huge loss, I heard) to Concert, which scooped it up with plans to build a shorter highrise that wouldn’t mar City Hall sightlines. 

I knew construction was imminent when the property was fenced off in late summer; pile driving equipment arrived on scene in late fall and hoarding went up over the Bay and Dundas Street sidewalks in late October and early November.

Below are pics of the Motion on Bay Street site, including some shots from 2008.

 

Motion on Bay Street apartments

Motion on Bay Street apartment site next to the One City Hall luxury apartment building (viewed here from the east side of Bay Street on September 26 2008)


Motion on Bay Street apartments

Another view of Motion on Bay Street apartment site on September 26 2008


Motion on Bay Street apartments

Motion on Bay Street apartment site fenced off in September 29 2010


Motion on Bay Street apartments

Motion on Bay Street apartment site fenced off in September 29 2010


Motion on Bay Street apartments

Pile drilling equipment operating on site November 23 2010


Motion on Bay Street apartment

Hoarding along Bay Street on November 23 2010


Motion on Bay apartments

Site viewed from the northeast corner of Bay & Dundas on November 23 2010


Motion on Bay Street apartments

Motion on Bay signs on hoarding along Dundas Street on November 23 2010


Motion on Bay Street apartments

Motion on Bay Street signs on Dundas Street hoardings November 23 2010


Motion on Bay Street apartments

Motion on Bay Street signs along Dundas Street on November 23 2010


Motion on Bay Street apartments

Dundas Street view towards Motion on Bay site November 23 2010


Motion on Bay Street apartments

Dundas Street view towards Motion on Bay site November 23 2010


Motion on Bay Street apartments

Bay Street view of the Motion on Bay site (left) on January 8 2011


Motion on Bay Street apartments

Bay Street view of the Motion on Bay site on January 8 2011


Motion on Bay Street apartments

Yellow excavator digging away on January 8 2011


Motion on Bay Street apartments

Excavation activity continuing on January 14 2011